Automatic Production Line of Fan Gear
 
Assembly Work
1.Swing Rod
2.Major Part
3.Big Gear
4.Lock screw
5.Examination
6.Oblique Gear
7.Filling Oil
8.Upper Cover
9.Lock screw
10.Examination
11.Take out good products
Production Speed:2 second/per unit
 



Automatic Production Line of Drawer Slide Track
Assembly Work
1.Grease external plate
2.Steel ball of medium plate
3.Rubber Pad of medium plate
4.Examination of pull and push
5.Bend
6.Rubber Block
Production Speed:4 second/per unit